Business Technology

Business Technology Dates
Project: Business Technology
Design: 12 Months 1-May-08 to 1-May-09
DSA: 6 Months 2-May-09 to 2-Nov-09
Bid and Award:
3 Months 3-Nov-09 to 3-Feb-10
Demolish S bldg: 3 Months 4-Feb-10 to 4-May-10
Duration: 18 Months
Start Date: 5-May-10
Finish Date 5-Nov-11
Business Technology Alerts
Project Name / Area Approximate: Business Technology
Start/Finish Dates: 08/01/2010 to 10/09/2012
Emergency Contact: Thomas J. Fine 619-994-4262, Guy Meades 619-994-5154, Rachel Fornaca - 619-994-8443, Paul Wraa- 858-922-5169
Construction Alert Description: Construction work began in 10/2010 and is ongoing in this area until late 2012. See "General Status" page for construction details.
 Comments:  Please notify City College Business Services for other alerts as observed.
Business Technology Status
Project: Business Technology
Description: New construction of approximately 40,000 sf for business department including new space for Business Studies, SIFE, Business and Computer Systems, Common Areas and associated support space.
Location: 16th Street & C Street.
Start Date: 8/26/2009
Finish Date: 10/9/2012
Phase: DSA review
Funding: N
Comments: ***See Humanities Bldg above***