D Building Roof

D Building Roof Dates
Activity: D Building Roof
Design: 7 Months 2-Jan-09 to 2-Aug-09
 DSA: 5 Months 3-Aug-09 to 3-Jan-10
 Bid and Award:
3 Months 4-Jan-10 to 4-Apr-10
Duration: 9 Months
Start Date: 5-Apr-10
Finish Date 5-Jan-11
D Building Roof Alerts
Project Name / Area Approximate: D Building Roof
Start Dates: TBD
Emergency Contact:
Construction Alert Description: AS OF APRIL 2011 PROJECT CONSTRUCTION HAS NOT STARTED
D Building Roof Status
Project: D Building Roof
Description: Replacement of the D Building roof. Includes refurbishment of existing rooftop pedestrian surface.
Location: Central Campus, Russ Blvd. adjacent to A Bldg.
Start Date: 7/15/2009
Finish Date: TBD
Phase: Design
Funding: N
Comments: As of 01/2011- Design began in July 2009 and Design has reached the 100% DD Phase. Architects and District Management met in 07/2010 to review project. Design requirements and scope have resulted in a large cost increase, and due to this increase, project budget, logistics, and project schedule are still TBD and being coordinated among design team and District Facilities Mgmt. A cost proposal including the new scope and design requirements has been approved by District Management, and they are now reviewing options to combine this project with the M Bldg Remodel Project.