M Building Renovation

M Building Dates
Project: M Building Renovation
Design: 12 Months 28-Oct-11 to 28-Oct-12
DSA: 6 Months 29-Oct-12 to 29-Apr-13
Bid and Award: 3 Months 30-Apr-13 30-Jul-13
Duration: 12 Months
Start Date: 31-Jul-13
Finish Date 31-Jul-14
M Building Alerts
Project Name / Area Approximate: M Building Renovation
Start Dates: approx. 1/2013 to 2/2014
Emergency Contact:
Construction Alert Description: AS OF APRIL 2011 PROJECT CONSTRUCTION HAS NOT STARTED
M Building Status
Project: M Building Renovation
Description: Renovation of approximately 15,000 sf for student support services, new bookstore, common areas and associated support space.
Location: B St. and Park Ave.
Start Date: 10/28/2010
Finish Date: 2/25/2014
Phase: Planning
Funding: N
Comments: As of 04/2011- The programming and conceptual design phase of the project began in 11/2010 with a kick-off meeting with the Campus held on 11/16/2010. Preliminary meetings with DSA have introduced the possibility of a total building seismic upgrade and the design team is in the process of reviewing the project and possibly combining it with the D Bldg Remodel in order to avoid a total seismic upgrade. As of 04/2011 and Per District Management's request, a fault study is being done by a geotechnical engineer to determine what action will be taken. This fault study is expected to be completed by the end of 04/2011. Design and planning meetings for this project will not resume until the fault study is complete and District Management has reviewed it's findings. Please note, renovation construction on the M Bldg cannot begin until Science Bldg construction is complete.