Project: Modular Village
Description: Installation of 12 temporary portable classrooms and a restroom facility to be used as "swing" space for construction improvements throughout the campus.
Location: Student Parking Lot #2
Start Date: 7/3/2006
Finish Date: 1/28/2008
Phase: Complete
Funding: S
Comments: As of 02/2011- In order to clear the way for the future Science Building site, and in order to provide contractor staging/laydown for the Central Plant and Storm Drain/Sewer Upgrade projects, the District hired a contractor to remove all of the T-Modular Classrooms.  These were then relocated to Mesa College and this work was completed the weekend of 9/18-9/19/2010.  The Contractor also installed fencing around the site and this will remain in place throughout the duration of the new Central Plant and Science Bldg construction.  As of 02/2011, Parking Lot #2 is closed and fenced off, in addition to Parking Lot #1, however ADA Parking, CACT/Incubator Parking, and a Pedestrian Walkway remain in the area of Parking Lot #1.  Vehicular access to the T Bldg lower-level manufacturing bays and Facilities Maintenance areas in the "canyon" will remain open during construction, which should last until approx. early/mid-2013.