Projected Dates

Project: Campus Master Plan
 Activity:  
Duration:  
Start Date:  
Finish Date:  
Skills Center Demolition Dates
Project: Skills Center Demolition
Design:
DSA:
Bid and Award:

Duration:
Start Date: 6/22/2010
Finish Date 10/11/2010
Modular Village Dates
Activity:
Duration:
Start Date:
Finish Date
L Building Dates
Activity: Construction
Duration: 13 months
Start Date:  25-Feb-08
Finish Date  1-Jun-09
P Building & Power Upgrade Project (Oct. 2010) Dates
Activity: Construction
Duration: 14 Months
Start Date: 12-May-08
Finish Date 10-Sept-09
CTC Dates
Bid and Award: 3Months 30-Mar-08 to 30-May-08
Duration: 18 Months
Start Date: 2-Jun-08
Finish Date 2-Nov-09
Infrastructure Upgrade Phase 1 Dates
Design: 14 Months 2-Apr-08 to 1-Jul-09
 DSA:  6 Months 2-Jul-09 to 31-Dec-09
 Bid and Award:
 2 Months 2-Jan-10 to 2-Mar-10
Duration: 13 Months
Start Date: 3-Mar-10
Finish Date 3-Apr-11
Math and Social Sciences Building Dates
Project: West Block Classrooms (General Purpose Classrooms)
Design: 13 Months 2-Apr-08 to 31-May-09
DSA:  6 Months 1-Jun-09 to 1-Dec-09
 Bid and Award:
2 Months 2-Dec-09 to 2-Feb-10 
Duration: 18 Months
Start Date: 3-Feb-10
Finish Date 3-Aug-11
D Building Roof Dates
Activity: D Building Roof
Design: 7 Months 2-Jan-09 to 2-Aug-09
 DSA: 5 Months 3-Aug-09 to 3-Jan-10
 Bid and Award:
3 Months 4-Jan-10 to 4-Apr-10
Duration: 9 Months
Start Date: 5-Apr-10
Finish Date 5-Jan-11
Humanities Building Dates
Project: Humanities Building
DSA:  6 Months 2-May-09 to 2-Nov-09
Bid and Award  3 Months 3-Nov-09 to 3-Feb-10
Duration: 21 Months
Start Date: 4-Feb-10
Finish Date 4-Nov-11
Business Technology Dates
Project: Business Technology
Design: 12 Months 1-May-08 to 1-May-09
DSA: 6 Months 2-May-09 to 2-Nov-09
Bid and Award:
3 Months 3-Nov-09 to 3-Feb-10
Demolish S bldg: 3 Months 4-Feb-10 to 4-May-10
Duration: 18 Months
Start Date: 5-May-10
Finish Date 5-Nov-11
Science Building Dates
Project:  Science Building
Design: 12 Months 1-Oct-08 to 1-Oct-09
 DSA: 6 Months 2-Oct-09 to 2-Apr-10
 Bid and Award:
3 Months 3-Apr-10 to 3-Jul-10
Duration: 24 Months
Start Date: 5-Jul-10
Finish Date 5-Jul-12
Infrastructure Upgrade Phase 2 Dates
Project: Infrastructure Upgrade Phase 2
Design:
12 29-Jun-09 to 29-Jun-10
 DSA: 6 30-Jun-10 to 30-Dec-10 
Duration: 12 Months
Start Date: 1-Apr-11
Finish Date 1-Apr-12
C Building Renovation Dates
Project: C Building Renovation
Design 12 Months 3-Feb-10 to 3-Feb-11
DSA: 6 Months 4-Feb-11 to 4-Aug-11
Bid and Award: 3 Months 5-Aug-11 to 5-Nov-11
Duration: 19 Months
Start Date: 6-Nov-11
Finish Date 6-Jun-13
T Building Dates
Project: Engineering Technology (T Bldg)
Design: 12 Months 3-Feb-10 to 3-Feb-11
DSA: 6 Months 4-Feb-11 to 4-Aug-11
Bid and Award: 3 Months 5-Aug-11 to 5-Nov-11
Duration: 19 Months
Start Date: 6-Nov-11
Finish Date 6-Jun-13
Child Development Center Dates
Project: Child Development Center
Design: 10 Months 28-Dec-10 to 28-Oct-11
DSA: 6 Months 29-Oct-11 to 29-Apr-12
Bid and Award: 3 Months 30-Apr-12 to 30-Jul-12
Duration: 12 Months
Start Date: 31-Jul-12
Finish Date 31-Jul-13
M Building Dates
Project: M Building Renovation
Design: 12 Months 28-Oct-11 to 28-Oct-12
DSA: 6 Months 29-Oct-12 to 29-Apr-13
Bid and Award: 3 Months 30-Apr-13 30-Jul-13
Duration: 12 Months
Start Date: 31-Jul-13
Finish Date 31-Jul-14
A Building Dates
Project: A Building Renovation
Design: 12 Months 27-Feb-12 to 27-Feb-13
DSA: 6 Months 28-Feb-13 to 29-Aug-13
Bid and Award:
3 Months 30-Aug-13 to 30-Nov-13
Duration: 13 Months
Start Date: 31-Nov-13
Finish Date 31-Dec-14