| Comments: |
As of 04/2011- Design complete in Spring 2010 and construction drawings submitted to DSA in 05/2011. The drawings were reviewed and returned by DSA in late 10/2010. Architects have addressed DSA comments and resubmitted drawings to DSA for final approval. Due to some unforeseeable conflicts regarding the Fire/Life Safety Review and Deferred Approval Items, DSA final approval has not been received as of 04/21/2011 but it anticipated by the end of 04/2011. The project began sitework and site preparation in 09/2010, with the removal of the modular classrooms, concrete curbs, retaining walls, and utilities. In 01/2011, Parking Lot #2 was closed and fenced off, in addition to Parking Lot #1, however ADA Parking, CACT/Incubator Parking, and a Pedestrian Walkway remain in the area of Parking Lot #1. Vehicular access to the T Bldg lower-level manufacturing bays and Facilities Maintenance areas in the "canyon" will remain open during construction, which should last until approx. early/mid-2013. Interior design planning meetings with Campus and Faculty were held in 11/2010 and the faculty selected their carpet, tile, and casework finishes. The FF&E process with District Purchasing, District FF&E Project Manager, and Campus Representatives is scheduled to begin in Summer 2011. As of 04/2011, The Project team is currently working to prepare the bidding documents with plans to be ready to bid the project in 05/2011 or 06/2011, depending on DSA final approval, with construction beginning soon thereafter.
|