Project:
West Block Classrooms
(General Purpose Classrooms)
Description: New
construction of approximately 73,000 sf for general
purpose classrooms, health center, chancellor's
conference center and associated support space. Also
includes the construction of a 400-car parking garage.
Location: 15th
Street & Broadway
Start Date:
4/2/2008
Finish Date:
8/30/2011
Phase: Planning
Funding: S
Comments: Project
is being prepared for a Design Build delivery. The RFP
proposals are due on Sept. 8th with an anticipated
selection date of Oct 24.
|