Building Your Future Today!
  Campus Master Plan
  R Building Renovation
  Modular Village
  Academic Success Center
(L Building)
  P Building Renovation
  Career Technology Center (CTC)
  Infrastructure Upgrade Phase 1
  General Purpose Classrooms
  D Building Roof
  Humanities Building
  Business Technology
  Science Building
  Infrastructure Upgrade Phase 2
  C Building Renovation
  Engineering Technology (T Bldg)
  Child Development Center
  M Building Renovation
  A Building Renovation

Project/Activity

Duration Start Date Finish Date
 

L Building Renovation

  
Construction 13months 25-Feb-08 1-Jun-09
P Building Renovation  

 

Bid & Award      
Construction 14months 12-May-08 10-Jul-09
Career Tech Center  

 

Bid & Award 3months 30-Mar-08 30-May-08
Construction 18months 2-Jun-08 2-Nov-09
Infrastructure Phase 1  

 

Design 14months 2-Apr-08 1-Jul-09
DSA 6months 2-Jul-09 31-Dec-09
Bid & Award 2months 2-Jan-10 2-Mar-10
Construction 13months 3-Mar-10 3-Apr-11
West Block Classrooms  

 

Design 13months 2-Apr-08 31-May-09
DSA 6months 1-Jun-09 1-Dec-09
Bid & Award 2months 2-Dec-09 2-Feb-10
Construction 18months 3-Feb-10 3-Aug-11
D Building Roof  

 

Design 7months 2-Jan-09 2-Aug-09
DSA 5months 3-Aug-09 3-Jan-10
Bid & Award 3months 4-Jan-10 4-Apr-10
Construction 9months 5-Apr-10 5-Jan-11
Humanities Building  

 

Design 12months 1-May-08 1-May-09
DSA 6months 2-May-09 2-Nov-09
Bid & Award 3months 3-Nov-09 3-Feb-10
Construction 21months 4-Feb-10 4-Nov-11
Business Technology  

 

Design 12months 1-May-08 1-May-09
DSA 6 months 2-May-09 2-Nov-09
Bid & Award S Bldg Demo 3 months 3-Nov-09 3-Feb-10
Demolish S bldg 3 months 4-Feb-10 4-May-10
Bid & Award 3 months 4-Feb-10 4-May-10
Construction 18 months 5-May-10 5-Nov-11
Science Building  

 

Design 12 months 1-Oct-08 1-Oct-09
DSA 6 months 2-Oct-09 2-Apr-10
Bid & Award 3 months 3-Apr-10 3-Jul-10
Construction 24 months 5-Jul-10 5-Jul-12
Infrastructure Phase 2  

 

Design 12 months 29-Jun-09 29-Jun-10
DSA 6 months 30-Jun-10 30-Dec-10
Bid & Award 3 months 31-Dec-10 31-Mar-11
Construction 12 months 1-Apr-11 1-Apr-12
C Building Renovation  

 

Design 12 months 3-Feb-10 3-Feb-11
DSA 6 months 4-Feb-11 4-Aug-11
Bid & Award 3 months 5-Aug-11 5-Nov-11
Construction 19 months 6-Nov-11 6-Jun-13
Eng Tech / T Bldg  

 

Design 12 months 3-Feb-10 3-Feb-11
DSA 6 months 4-Feb-11 4-Aug-11
Bid & Award 3 months 5-Aug-11 5-Nov-11
Construction 19 months 6-Nov-11 6-Jun-13
Child Dev Center  

 

Design 10 months 28-Dec-10 28-Oct-11
DSA 6 months 29-Oct-11 29-Apr-12