Project/Activity |
Duration |
Start Date |
Finish Date |
|
L Building Renovation |
|
|
Construction |
13months |
25-Feb-08 |
1-Jun-09 |
|
P Building Renovation |
|
|
Bid & Award |
|
|
|
|
Construction |
14months |
12-May-08 |
10-Jul-09 |
|
Career Tech Center |
|
|
Bid & Award |
3months |
30-Mar-08 |
30-May-08 |
|
Construction |
18months |
2-Jun-08 |
2-Nov-09 |
|
Infrastructure Phase 1 |
|
|
Design |
14months |
2-Apr-08 |
1-Jul-09 |
|
DSA |
6months |
2-Jul-09 |
31-Dec-09 |
|
Bid & Award |
2months |
2-Jan-10 |
2-Mar-10 |
|
Construction |
13months |
3-Mar-10 |
3-Apr-11 |
|
West Block Classrooms |
|
|
Design |
13months |
2-Apr-08 |
31-May-09 |
|
DSA |
6months |
1-Jun-09 |
1-Dec-09 |
|
Bid & Award |
2months |
2-Dec-09 |
2-Feb-10 |
|
Construction |
18months |
3-Feb-10 |
3-Aug-11 |
|
D Building Roof |
|
|
Design |
7months |
2-Jan-09 |
2-Aug-09 |
|
DSA |
5months |
3-Aug-09 |
3-Jan-10 |
|
Bid & Award |
3months |
4-Jan-10 |
4-Apr-10 |
|
Construction |
9months |
5-Apr-10 |
5-Jan-11 |
|
Humanities Building |
|
|
Design |
12months |
1-May-08 |
1-May-09 |
|
DSA |
6months |
2-May-09 |
2-Nov-09 |
|
Bid & Award |
3months |
3-Nov-09 |
3-Feb-10 |
|
Construction |
21months |
4-Feb-10 |
4-Nov-11 |
|
Business Technology |
|
|
Design |
12months |
1-May-08 |
1-May-09 |
|
DSA |
6 months |
2-May-09 |
2-Nov-09 |
|
Bid & Award S Bldg Demo |
3 months |
3-Nov-09 |
3-Feb-10 |
|
Demolish S bldg |
3 months |
4-Feb-10 |
4-May-10 |
|
Bid & Award |
3 months |
4-Feb-10 |
4-May-10 |
|
Construction |
18 months |
5-May-10 |
5-Nov-11 |
|
Science Building |
|
|
Design |
12 months |
1-Oct-08 |
1-Oct-09 |
|
DSA |
6 months |
2-Oct-09 |
2-Apr-10 |
|
Bid & Award |
3 months |
3-Apr-10 |
3-Jul-10 |
|
Construction |
24 months |
5-Jul-10 |
5-Jul-12 |
|
Infrastructure Phase 2 |
|
|
Design |
12 months |
29-Jun-09 |
29-Jun-10 |
|
DSA |
6 months |
30-Jun-10 |
30-Dec-10 |
|
Bid & Award |
3 months |
31-Dec-10 |
31-Mar-11 |
|
Construction |
12 months |
1-Apr-11 |
1-Apr-12 |
|
C Building Renovation |
|
|
Design |
12 months |
3-Feb-10 |
3-Feb-11 |
|
DSA |
6 months |
4-Feb-11 |
4-Aug-11 |
|
Bid & Award |
3 months |
5-Aug-11 |
5-Nov-11 |
|
Construction |
19 months |
6-Nov-11 |
6-Jun-13 |
|
Eng Tech / T Bldg |
|
|
Design |
12 months |
3-Feb-10 |
3-Feb-11 |
|
DSA |
6 months |
4-Feb-11 |
4-Aug-11 |
|
Bid & Award |
3 months |
5-Aug-11 |
5-Nov-11 |
|
Construction |
19 months |
6-Nov-11 |
6-Jun-13 |
|
Child Dev Center |
|
|
Design |
10 months |
28-Dec-10 |
28-Oct-11 |
|
DSA |
6 months |
29-Oct-11 |
29-Apr-12 |
| |